e8vk
UNITED STATES
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
FORM 8-K
CURRENT REPORT
Pursuant to Section 13 or 15(d) of
the Securities Exchange Act of 1934
Date of
Report (Date of earliest event reported): October 8, 2008
CENTERPOINT ENERGY, INC.
(Exact name of registrant as specified in its charter)
|
|
|
|
|
Texas
(State or other jurisdiction
of incorporation)
|
|
1-31447
(Commission File Number)
|
|
74-0694415
(IRS Employer
Identification No.) |
|
|
|
1111 Louisiana
Houston, Texas
(Address of principal executive offices)
|
|
77002
(Zip Code) |
Registrants telephone number, including area code: (713) 207-1111
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
(Exact name of registrant as specified in its charter)
|
|
|
|
|
Texas
(State or other jurisdiction
of incorporation)
|
|
1-3187
(Commission File Number)
|
|
22-3865106
(IRS Employer
Identification No.) |
|
|
|
1111 Louisiana
Houston, Texas
(Address of principal executive offices)
|
|
77002
(Zip Code) |
Registrants telephone number, including area code: (713) 207-1111
CENTERPOINT ENERGY RESOURCES CORP.
(Exact name of registrant as specified in its charter)
|
|
|
|
|
Delaware
(State or other jurisdiction
of incorporation)
|
|
1-13265
(Commission File Number)
|
|
76-0511406
(IRS Employer
Identification No.) |
|
|
|
1111 Louisiana
Houston, Texas
(Address of principal executive offices)
|
|
77002
(Zip Code) |
Registrants telephone number, including area code: (713) 207-1111
Check the appropriate box below if the Form 8-K filing is intended to simultaneously satisfy
the filing obligation of the registrant under any of the following provisions (see General
Instruction A.2. below):
o Written communications pursuant to Rule 425 under the Securities Act (17 CFR 230.425)
o Soliciting material pursuant to Rule 14a-12 under the Exchange Act (17 CFR 240.14a-12)
o Pre-commencement communications pursuant to Rule 14d-2(b) under the Exchange Act (17
CFR 240.14d-2(b))
o Pre-commencement communications pursuant to Rule 13e-4(c) under the Exchange Act (17
CFR 240.13e-4(c))
Item 8.01 Other Events.
As of October 1, 2008, CenterPoint Energy, Inc.s (CenterPoint Energy) electric transmission
and distribution subsidiary, CenterPoint Energy Houston Electric, LLC (CenterPoint Houston) had
restored service to approximately 99 percent of its customers following Hurricane Ike. Over 90
percent of CenterPoint Houstons over 2 million customers initially were without electric service
after Hurricane Ike struck CenterPoint Houstons service territory on September 13. Restoration
work continues for a relatively small number of customers, including customers needing
customer-owned equipment repairs. Many of the remaining outages involve customers who are unable
to receive electric service due to damaged electrical equipment or flooding. In addition to
working to restore service to remaining customers, CenterPoint Houston personnel are inspecting
work that has been done and making long term repairs where temporary repairs were made during the
initial stage of the restoration effort. CenterPoint Houston is now phasing down its field
workforce, which totaled as many as 13,000 personnel from among its own employees and utilities
and contractors across the United States and Canada.
Some restoration and repair work is expected to continue during most of the remainder of 2008,
as customers rebuild homes and other facilities that were severely damaged by the storm. Although
CenterPoint Houstons facilities were most severely damaged in heavily wooded areas, the most
serious damage to customer facilities tended to be concentrated in immediate coastal areas, such as
Galveston Island, which received damage both from Hurricane Ikes strong winds and the associated
tidal surge.
Total costs for the restoration effort still cannot be measured with precision, but
CenterPoint Houston now estimates that its costs will be in the range of approximately $650 million
to $750 million. Although the poles, towers, wires, street lights and the pole mounted equipment
that comprise CenterPoint Houstons transmission and distribution system are not covered by
property insurance, office buildings and warehouses and their contents and substations and their
associated facilities are covered by insurance that provides for a maximum deductible of $10
million. Current estimates are that total losses to property covered by this insurance were
approximately $25 million.
As reported previously, CenterPoint Houston is deferring the uninsured storm restoration costs
in the expectation of recovery through the regulatory process. As a result, storm restoration
costs will not affect CenterPoint Energys or CenterPoint Houstons reported net income for 2008.
Assuming necessary enabling legislation is enacted by the Texas Legislature in the session which
begins in January 2009, CenterPoint Houston expects to obtain recovery of its storm restoration
costs through the issuance of non-recourse securitization bonds similar to the storm recovery bonds
issued by another Texas utility following Hurricane Rita. When those bonds are issued, CenterPoint
Houston would recover the amount of storm restoration costs approved by the Public Utility
Commission of Texas out of the bond proceeds, with the bonds being repaid over time through a
charge imposed on customers. Alternatively, if securitization is not available, recovery of those
costs would be sought through traditional regulatory mechanisms. Under its 2006 rate case
settlement, CenterPoint Houston is entitled to seek an adjustment to rates in this situation, even
though in most instances its rates are frozen until 2010.
In addition to storm restoration costs, CenterPoint Houston has lost revenue during the outage
period, and will continue to lose some revenue that would otherwise have been anticipated from
those customers whose service will not be restored for a longer period. As of October 1,
CenterPoint Houston has restored all but a minor portion of the load on its system, but the temporary
outages caused by the storm are expected to have a negative impact on CenterPoint Energys and
CenterPoint Houstons earnings for the third quarter and for the full year 2008. However, the exact amount
of these impacts cannot be determined at this time.
CenterPoint Energy and CenterPoint Houston continue to believe that they have sufficient
liquidity to finance storm restoration costs until ultimate recovery, while at the same time
carrying out their current business plans. If storm cost recovery is delayed substantially,
CenterPoint Energy and CenterPoint Houston could be required to reduce funding on planned projects or to
seek capital resources not currently planned.
Capacity and usage of existing bank credit facilities of CenterPoint Energy and CenterPoint Houston
as of September 30, 2008 are shown in the table below (in millions).
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Size of |
|
Amount Utilized |
|
Amount Remaining |
Company |
|
Facility |
|
at 9/30/2008 |
|
at 9/30/2008 |
CenterPoint Energy
|
|
$ |
1,200 |
|
|
$ |
180 |
|
|
$ |
1,020 |
|
CEHE
|
|
$ |
300 |
|
|
$ |
174 |
|
|
$ |
126 |
|
Also, CenterPoint Houston may obtain funds to finance costs associated with its overall
liquidity requirements or to reduce usage of bank credit facilities through the issuance of general
mortgage bonds or other capital markets transactions.
In addition, CenterPoint Energy Resources Corp. (CERC), the natural gas subsidiary of
CenterPoint Energy, has its own $950 million bank credit facility, of which $745 million was
utilized at September 30, 2008. This facility is available to fund CERCs business requirements,
including the minimal impact to CERC facilities from Hurricane Ike. The CERC facility would not be
used to fund CEHEs hurricane restoration costs.
The term of each credit facility extends to 2012. Amounts utilized are subject to certain
covenants, but based on unaudited financial information, CenterPoint Energy and CenterPoint Houston
believe they would have been entitled to utilize substantially all of the capacity under their
respective credit facilities at September 30, 2008. However, Lehman Brothers Bank, FSB, whose parent has
filed for bankruptcy protection, has an approximately four percent participation in each of the
facilities but has not been funding its commitments following the bankruptcy filing, effectively
causing a minor reduction to the total available capacity under the three facilities.
SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly
caused this report to be signed on its behalf by the undersigned hereunto duly authorized.
|
|
|
|
|
|
CENTERPOINT ENERGY, INC.
|
|
Date: October 8, 2008 |
By: |
/s/ Rufus S. Scott
|
|
|
|
Rufus S. Scott |
|
|
|
Senior Vice President, Deputy
General Counsel and Assistant
Corporate Secretary |
|
|
SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly
caused this report to be signed on its behalf by the undersigned hereunto duly authorized.
|
|
|
|
|
|
CENTERPOINT ENERGY HOUSTON ELECTRIC, LLC
|
|
Date: October 8, 2008 |
By: |
/s/ Rufus S. Scott
|
|
|
|
Rufus S. Scott |
|
|
|
Senior Vice President, Deputy
General Counsel and Assistant
Corporate Secretary |
|
|
SIGNATURE
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly
caused this report to be signed on its behalf by the undersigned hereunto duly authorized.
|
|
|
|
|
|
CENTERPOINT ENERGY RESOURCES CORP.
|
|
Date: October 8, 2008 |
By: |
/s/ Rufus S. Scott
|
|
|
|
Rufus S. Scott |
|
|
|
Senior Vice President, Deputy
General Counsel and Assistant
Corporate Secretary |
|
|